Let the total work be 90 units (lcm of 18 and 15)

Efficiency of Dave =90/18 =5 units

Efficiency of Brian= 90/15 =6 units

Brian worked for 10 days therefore 6 x 10 =60 units work is done.

Remaining work = 90-60 =30 units.

Dave would take 30/5 =6 days to complete to remaining work.