Determine Float Value for an activity x
which takes duration of 14 days,
and it started 7 days earlier to its scheduled date and completed on 42nd
day of the project schedule,
0.7 days
28 days
35 days
None of these
Answers
Answered by
0
Answer:
None of these
Explanation: