Determine Float Value for an activity x
which takes duration of 14 days,
and it started 7 days earlier to its scheduled date and completed on 42nd
day of the project schedule,
0.7 days
28 days
35 days
None of these​

Answers

Answered by Anonymous
0

Answer:

None of these