Math, asked by badshah84, 5 months ago

Dheeraj can do a work in 9 days and Sunil in 15 days. if they work on it together for 5 days then the fraction on the work that is left, is​

Answers

Answered by amrutanshu50
1

Hey buddy!!

Please refer to the above image for solution!!

Thank you!!

Attachments:
Answered by bson
1

Step-by-step explanation:

D does work in 9 days

=> D in 1 day does 1/9 part of work

S does work in 15 days

=> S in 1 day does 1/15 part of work

D+S = 1/9 +1/15 = 5+3/45=8/45

=> In 1 day, D+S does 8/45 part of work

In 5 days, D+S does 5×8/45 =8/9 part of work

remaining work =1- 8/9 = 1/9