dhruvin completes a work in 8 hours of instead of 10 hours. labor rate per hour is rs 5. what he will earn as per Rowan plan? please answer
Answers
Answered by
2
ANSWER :
- ❖ If Dhruvin completes a work in 8 hours of instead of 10 hours and labour rate per hour is Rs. 5; then as per Rowan plan, he will earn Rs. 8.
___________________________________________________________
SOLUTION :
❒ Given :-
- Dhruvin completes a work in 8 hours of instead of 10 hours.
- Labour rate per hour is Rs. 5.
❒ To Calculate :-
- Bonus as per Rowan Plan = ?
❒ Formula :-
- Bonus under Rowan System is calculated as under :
_______________________________________________
❒ Calculation :-
Here,
- Time Taken = 8 hours
- Time Allowed = 10 hours
So,
- ✠ Time Saved = Time Allowed - Time Taken
➨ Time Saved = 10 hours - 8 hours
➨ Time Saved = 2 hours
Now,
- Time Saved = 2 hours
- Rate Per Hour = Rs. 5
Using the formula of Bonus under Rowan System, we get,