Differentiate between Core, Supporting and facilitating services?

Answers

Answered by rajan521
1

Answer:

please mark as briliant answer

______________________________

Core processes have planning dependencies that require them to be performed in the same sequence on most projects. The core planning processes may be repeated several times during the project. For example, project work must be defined before it is scheduled and resources are assigned to it.

Facilitating processes are different from core processes because they are performed intermittently throughout the project rather than in a specific order. These planning processes are itemized later in the chapter.