Math, asked by rakshithhegde1998, 5 months ago


Dilip and Samrat can do a piece of work in 16 days and 24 days
respectively. Samrat works alone for 15 days and leaves. In how many
days can Dilip complete the remaining work?​

Answers

Answered by Anonymous
1

Step-by-step explanation:

dilip = 16d

samrat = 24d

total =48W

efficiency of Dilip =3

efficiency of samrat =2

samrat 15 days work = 15×2

=30W

remaining =48-30

= 18W

dilip = 18/3 = 6 days

Similar questions