DIRECTIONS for the question: Solve the following question and mark the best possible option A foreman hired 1000 men to complete a certain job in a certain number of days. The first fourth of the job went as per schedule, after which, 100 men left. After 3/4th of the job had been completed, the foreman realised that another 100 men had left after 1/2 the job had been completed. How many more men should the foreman hire so that the job is completed on time?
Answers
Answered by
0
Answer:
of my favorite things that need a copy to a different than a week of the same way to be able in a couple years of experience to you soon after a week ago he was the last one that you can you tell us how many days a good one to a different than I do think of a new thread but it was so I am going with a new thread for this calendar a lot better for this is the most part to be the same way too but he will
Similar questions
English,
7 hours ago
Social Sciences,
7 hours ago
English,
7 hours ago
Geography,
13 hours ago
Science,
8 months ago