due to fever efficiency of ramesh is reduced by 40% hence he takes 12 more days than earlier to complete . if next day he start working with 50 % of his original efficiency. now in how many days will complete the total work ​?

Answers

Answered by RDGAMERYTL
0

Answer:

Follow for more and subscribe to my channel RD GAMER YTL please

Step-by-step explanation:

Here, i have considered the question as Ram's efficiency reduced to 40% not reduced by 40% . Because, it's given that when he starts next, his efficiency level is 50% ie efficiency has increased.

There are many methods to work out such problems.

Suppose , with his full efficiency , Ram completes ..

10 work …. in x days

Since efficiency level is 40% now

So, 4 work is done in x days

=> 10 work is done in (10x/4)days

& as per condition given

10x/4 - x = 12

=> 6x/4 = 12

=> x = 48/6 = 8 days

=> with full efficiency Ram completes the work in 8 days

With 40% efficiency Ram completes the work in (10*8)/4 = 20 days

& with 50% efficiency, if he starts a fresh , Ram will take 8 ÷ 1/2 = 16 days