"Dummies cannot be removed whenever it results in two or more activities that run between the same two

start and finish nodes". This rule is called as ?

(A) Overriding rule

(B) Oversizing rule

(C) Downsizing rule

(D) Overdriving rule​

Answers

Answered by palakchordiya123
2

Explanation:

(B) Oversizing rule is the answer

Answered by nidaeamann
4

Explanation:

Among the various options given in question statement the correct answer is option B, that is Oversizing rule.

When two or more activities are to run in parallel having same start and finish nodes, then it becomes important to keep their sizes same and this is done by oversizing them with dummies( the network which has less entries than the other).