Dummies cannot be removed whenever it results in two or more activities that run between the same two
start and finish nodes". This rule is called as ?
(A) Overriding rule
(B) Oversizing rule
(C) Downsizing rule
(D) Overdriving rule
2. Which must be sufficient to reveal scheduling restraints and important predecessor relationships?
(A) Reduntant activities
(B) Level of dummies
(C) Level of detail
(D) Level of predecessors
3. Which networks are constructed without use of dummies?
(A) AON
(B) AOA
(C) CPM
(D) PERT
4. Which kind of network is produced by both AON and AOA formats?
(A) Result-oriented network
(B) Activity-oriented network
(C) Task-oriented network
(D) Event-oriented network
5. A network is developed by starting with a list of activities and their?
(A) Immediate successors
(B) Immediate connectors
(C) Immediate predecessors
(D) Immediate precursors
6. What is the major use of network in project planning?
(A) Scheduling
(B) Supervision
(C) Error fixing
(D) On time completion
7. The expected project duration is determined by finding which path through the network?
(A) Shortest
(B) Longest
(C) Thinnest
(D) Thickest
8. The longest path from the origin node to the terminal node is called ?
Answers
Answered by
0
Answer:
OMG
Explanation:
So much sorry I cant....
sorry sorry
Similar questions
English,
1 month ago
Biology,
1 month ago
Math,
3 months ago
Hindi,
3 months ago
Political Science,
9 months ago