Math, asked by Hangasagar1, 1 year ago

duration= 21 days. finishing date = 12 Jan. find the starting date

Answers

Answered by pandukasam
3
the starting date will be Dec 22 because till january 1st 12 days are done
So the remaining 9 days are to be subtracted from 31 of december
Answered by jmmb
0
ans. 22 december
lets first substract 12 from 21
and then substract 9 from the previous month ....