Duration along the critical path defines which of the following ?1. Shortest duration needed2. Shortest duration permissible3. Longest duration needed4. Longest duration permissibleSelect the correct answer using the code given below :
A. 1 and 2 only B. 1 and 4 only C. 2 and 3 only D. 3 and 4 only
Answers
Answered by
0
2. Shortest duration permissible
Similar questions