Physics, asked by anjalipant8541, 1 year ago

during an active sprint who into what artifact and in which ceremony is new work or further decomposition of work added to the sprint backlog?

Answers

Answered by Answers4u
0

In Agile methodology, sprint is the basic unit of scrum and the scrum master is one who decides the duration of each sprint.

Three important acrtifacts of the scrum are product backlog, sprint backlog and product increment.

In active sprint, a new work or any further decomposition of the work will be added to the sprint backlog during the daily scrum, soon after the approval is received from the development team of the project.

Answered by SarcasticKarma
1

Answer:

Answer

  • In Agile methodology, sprint is the basic unit of scrum and the scrum master is one who decides the duration of each sprint.
  • Three important acrtifacts of the scrum are product backlog, sprint backlog and product increment.
  • In active sprint, a new work or any further decomposition of the work will be added to the sprint backlog during the daily scrum, soon after the approval is received from the development team of the project.
Similar questions