(e) Roll charts, etc.
(a) Produc-Trol Board
B.
There are seven jobs which are to be processed first on Mac
Process time in hours is given below. Find the optimal sequen
Task
A
B
С
D
E
F
Machine 1
6
24
30
12
20
22
18
Machine 2
1620
20
13
24
2
6.
Find the optimal sequence and total elapsed time. Compute the idle tim
sequence (as per the Johnson's algorithm) is:​