Math, asked by Sachinsaini76821, 11 months ago

Ed can do a piece of work in 8 hours. Edd can do the same work in 10 hours, eddy can do the same work in 12 hours. Ed, edd and eddy start the same work at 9 am, while ed stops at 11



a.M., the remaining two complete the work. At what time(approx) will the work get completed

Answers

Answered by HEMANTHKUMAR007
4
HEY MATE HERE IS YOUR ANSWER
Attachments:
Answered by shajilkjoshy
0

Answer:

The work will be completed by 1 pm.

Step-by-step explanation:

Ed can do the work in 8 hours

Edd can do the work in 10 hours

Eddy can do the work in 12 hours

In one hour:

Ed does \frac{1}{8} of the work.

Edd does \frac{1}{10} of the work.

Eddy does \frac{1}{12} of the work.

Let us denote the fraction of work completed by the three from 9 am to 11 am (2 hours) with A.

A = 2 \times (\frac{1}{8} + \frac{1}{10} + \frac{1}{12})

  = \frac{1}{4}+\frac{1}{5}+\frac{1}{6}

  = \frac{15 + 12 + 10}{60}

A = \frac{37}{60}

Remaining work, B = 1 - A

                           B  = \frac{23}{60}

The fraction of work Edd and Eddy together does in an hour = \frac{1}{10}+\frac{1}{12} = \frac{6+5}{60} = \frac{11}{60}

The time required for Edd and Eddy to do the remaining \frac{23}{60} of the work, T = \frac{23}{60}÷ \frac{11}{60}

T = \frac{23}{60} \times \frac{60}{11} = \frac{23}{11} \approx 2

Edd and Eddy requires approximately 2 hours for doing the remaining work. Thus the work can be completed 2 hours after 11 am, i.e. 1 pm.

The work will be complete by 1 pm.

#SPJ2

Similar questions