Math, asked by phaddy9220, 1 year ago

efficiency of a is 25% more than b and b takes 25 days to complete a piece of work. a started a work alone and then b joined her 5 days before actual completion of the work. for how many days a worked alone?

Answers

Answered by santy2
4

b works for 25 days to complete a piece of work.


Since a is 25% efficient than b, a will take less days by 25% to complete the work.


75/100 × 25 = 18.75 days


b joined 5 days before completion.


18.75 - 5 = 13.75 days


13.75 days that a work alone