Eight men and 12 boys can finish a piece of work in 10 days, while 6men and 8 boys can finish it in 14 days. Find the time taken by one boy alone to finish the work. ​

Answers

Answered by NiharikaThokala97
1

Step-by-step explanation:

MATHS

If 8 men and 12 boys can finish a piece of work in 10 days while 6 men and 8 boys can finish it in 14 days. Find the time taken by one man alone and that by one boy alone to finish the work.

Share

Study later

ANSWER

Suppose that one man alone can finish the work in x days and one boy alone can finish it in y days. Then,

One man's one day's work =

x

1

One boy's one day's work =

y

1

∴ Eight men's one day's work =

x

8

12 boy's one day's work =

y

12

Since 8 men and 12 boys can finish the work in 10 days

10(

x

8

+

y

12

)=1⇒

x

80

+

y

120

=1 ..(i)

Again, 6 men and 8 boys can finish the work in 14 days.

∴14(

x

6

+

y

8

)=1⇒

x

84

+

y

112

=1 (ii)

Putting

x

1

=u and

y

1

=v in equations (i) and (ii), we get

80u+120v−1=0

84u+112v−1=0

By using cross-multiplication method, we have

−120+112

u

=

−80+84

−v

=

80×112−120×84

1

−8

u

=

−4

v

=

−1120

1

⇒u=

−1120

−8

=

140

1

and v=

−1120

−4

=

280

1

Now, u=

140

1

x

1

=

140

1

⇒x=140

and, v=

280

1

y

1

=

280

1

⇒y=280.

Thus, one man alone can finish the work in 140 days and one boy alone can finish the work in 280 days.

Answered By

Answered by Anonymous
1

Answer:

one boy can finish the work in 280 days