Math, asked by pavithran12121995, 6 days ago

Eight Person can finish a work in 20 days . After 5 Days they were requested to complete the work in next 8 days . How many more persons should Join the group to fullfill the requirement ? ​

Answers

Answered by TigerMan28
0

Answer:

7 people

Step-by-step explanation:

Work done by 1 person in a day = 1/160

Work done by 8 people in 5 days = 40 / 160

Work left = 120 / 160

Time to be taken to complete the remaining work = 8 days

No. of people needed = 120 / 160 × 160 × 1/8

= 15

People needed more = 15 - 8 = 7 people

Hope it helps.

Answered by gouridaskar901
0

Answer:

As we know M1 muliple D1= M2 muliple D2 into 8 multiple 15=M2 multiple 8 into M2 = 15 therefore number of extra people 15 - 8 = 7