ES and EF are computed by taking?ES and EF are computed by taking?
Answers
Answered by
4
Answer:
To Calculate ES and EF times:
Label ES = zero at the start of the project.
Label EF = 0 + activity time for activities without any preceding activities. ...
Label ES for each activity, all of whose predecessors have been labeled = Maximum of {EF times of all immediately preceding activities including dummy activities}
Answered by
0
Answer:
To Calculate ES and EF times:
- Label ES = zero at the start of the project.
- Label EF = 0 + activity time for activities without any preceding activities. ...
- Label ES for each activity, all of whose predecessors have been labeled = Maximum of {EF times of all immediately preceding activities including dummy activities}