Science, asked by suryanarayana932, 7 months ago

. ______ estimate is based on cost per usable unit from past projects.

A. Unit price estimate

B. ROM (Rough Order of Magnitude) estimate

C. Assemblies estimate

D. SF estimate with modeled SF cost data

2. The assemblies estimate adjusts for quality by _______.

A. The specific method or material chosen

B. The use of ¼, median, and ¾ prices

C. The use of quality indices

D. The use of the cheapest materials

3. Which of the following estimate is typically used for Value Engineering?

A. Unit price estimate

B. Assemblies estimate

C. ROM (Rough Order of Magnitude) estimate

D. SF estimate with modeled SF cost data

4. UNIFORMAT is based on ______, and MasterFormat is based on ________.

A. Type of fundamental materials, and type of materials

B. Volume of each space, and area of living space

C. Materials, and type of occupancy

D. Functions of building component, and work results

Answers

Answered by shivtanu21
0

25 thanks + follow = inbox

.

.

.

.

.

.

.

.

plz Mark my answer as BRAINLIEST

Similar questions