Estimated loc count is 56,100 . Assuming that your organization produces 450 loc/pm with a burdened labor rate of $7000 per person-month, find the cost /loc, total estimated project cost and estimated effort in person months.
Answers
Answered by
0
Explanation:
Development of a software system P:
– Estimated lines of code of P : 33, 480 LOC
– Average productivity for P : 620 LOC per person-month
– Number of software developers : 6
– Average salary of a software developer : ` 50,000 per month
If E, D and C are the estimated development effort (in person-months), estimated development time (in months), and estimated development cost (in ` Lac) respectively, then (E, D, C) =_________.
(A) (48, 8, 24)
(B) (54, 9, 27)
(C) (60, 10, 30)
(D) (42, 7, 21)
Answer: (B)