Estimated loc count is 56,100 . Assuming that your organization produces 450 loc/pm with a burdened labor rate of $7000 per person-month, find the cost /loc, total estimated project cost and estimated effort in person months.

Answers

Answered by rocky364
0

Explanation:

Development of a software system P:

– Estimated lines of code of P : 33, 480 LOC

– Average productivity for P : 620 LOC per person-month

– Number of software developers : 6

– Average salary of a software developer : ` 50,000 per month

If E, D and C are the estimated development effort (in person-months), estimated development time (in months), and estimated development cost (in ` Lac) respectively, then (E, D, C) =_________.

(A) (48, 8, 24)

(B) (54, 9, 27)

(C) (60, 10, 30)

(D) (42, 7, 21)

Answer: (B)