1. Twelve carpenters working 10 hours a day complete a furniture work in 18 days.
How long would it take for 15 carpenters working for 6 hours per day to complete
the same piece of work?
An identical mobiles in 6 hours How many


this is compound variation​

Answers

Answered by amishatanu2197
3

Answer:24 days

Step-by-step explanation: