A can finish a work in 6 days and B can finish the same work in 12 days. Find the number
by A and B to finish the work, if they work together.
Answers
Step-by-step explanation:
this is your question-
A can finish a work in 6 days and B can finish the same work in 12 days. Find the number
A can finish a work in 6 days and B can finish the same work in 12 days. Find the numberby A and B to finish the work, if they work together.
solution-
time taken by a to complete the work = 6 days
a's 1 day's work = 1/6
time taken by b to complete the work =12 days
b's 1 day,s work=1/12
a's 1 days work + b's 1 days work = 1/6 + 1/12 =3/12 = 1/4
work done by them in 1 day = 1/4
they will together complete the work in 4 days.
i hope this help you
Answer:
knowledge is the key to success
Step-by-step explanation:
In physics, a force is any interaction that, when unopposed, will change the motion of an object. A force can cause an object with mass to change its velocity, i.e., to accelerate. Force can also be described intuitively as a push or a pull. A force has both magnitude and direction, making it a vector quantity.