1. Aman and Akash can do a piece of work in 12 and 15 days, respectively. In how many days can they
together finish the work?
Answers
Answered by
1
Answer:
1/number of days require = 1/12+1/15
= (5+4)/60 = 9/60 = 3/20
so number of days required = 20/3
Step-by-step explanation: