Father alone can finish work in 15 days and son is 50℅ more efficient than father in how many days will the work get finjshed if both work together
Answers
Answered by
6
Given :
Father takes - 15 days
Work done by father in 1 day = 1/15
_______________________________
Son is 50% efficient -
= 50/100 x 15 = 7.5 days .
work done by son in 1 day =
= 1/7.5 = 2/15.
_________________________________
If they work together -
1/15 + 2/15 = 3/15
_________________________________
Finding number of days -
3/15 of the work = 1 day
15/15 of the work = ?
= 15/15 x 15/3 = 5 days.
Hence:
If they work together they can
complete in 5 days.
Father takes - 15 days
Work done by father in 1 day = 1/15
_______________________________
Son is 50% efficient -
= 50/100 x 15 = 7.5 days .
work done by son in 1 day =
= 1/7.5 = 2/15.
_________________________________
If they work together -
1/15 + 2/15 = 3/15
_________________________________
Finding number of days -
3/15 of the work = 1 day
15/15 of the work = ?
= 15/15 x 15/3 = 5 days.
Hence:
If they work together they can
complete in 5 days.
Answered by
6
Father takes 15 days
⇒ 1 day = 1/15 of the work
Son is 50% more efficient
⇒ Son needs 0.5 x 15 = 7.5 days
⇒ 1 day = 1 ÷ 7.5 = 2/15 of the work
If the worked together:
1 day = 1/15 + 2/15 = 3/15 of the work
Find the number of days they need:
3/15 of the work = 1 day
1/15 of the work = 1 ÷ 3 = 1/3 day
15/15 of the work = 1/3 x 15 = 5 days
Answer: They will need 5 days if they worked together.