Find an optimal sequence of the following four - Jobs five machines, when passing is not allowed, given the following processing times. Also find the total elapsed time. Jobs Machine 1 2 3 4 M 6 5 4 7 M 4 5 2 2 M 1 3 4 2 M, 4 2 4 5 1 ME 8 9 7 5