Find the starting date for the following activities
c. Finishing date = 14th November
Time duration = 40 days
Answers
Answered by
2
Answer:
The answer
will be 5 October
Answered by
2
Answer:
6th October
Step-by-step explanation:
So the Finish date of 14 November is day 40
November 14 = October + 14 days = 31 +14 = 45 days
45 - 40 = 5th October but that would day 0, the day before the project started
6th October would be day 1 which is the start (note there is no day 0)