Find the starting date for the following activities

c. Finishing date = 14th November
Time duration = 40 days​

Answers

Answered by sy8900466464
2

Answer:

The answer

will be 5 October

Answered by brendanharkin
2

Answer:

6th October

Step-by-step explanation:

So the Finish date of 14 November is day 40

November 14 = October + 14 days = 31 +14 = 45 days

45 - 40 = 5th October but that would day 0, the day before the project started

6th October would be day 1 which is the start (note there is no day 0)