Math, asked by premshankarmaheta197, 6 months ago

Find the starting/ending data (not including given data). (a) Time taken =28 days, Ending date is 10th January.​

Answers

Answered by jyotipatar01
6

Step-by-step explanation:

here is the answer of this question

Attachments:
Answered by jayshreekalita
1

Step-by-step explanation:

9th january-1st january=9 days

Remaining days=28-9 days=19 days

31st December-13 th december=19 days

Starting date is 13 th december