Math, asked by man8496, 1 year ago

find the time duration for the following activities starting date 26th July finishing date 25th September

Answers

Answered by shivamsingh146071
2
no of days
July to aug :-5
aug to sep:-30
sep to given :- 25

total no of days :-60

time duration :- 60*24 h
=1440h

man8496: only july to sep
shivamsingh146071: july se sep hi hai
Answered by scchinna007
0

Answer:

Step-by-step explanation:

No. of days from 26th July to 31st July = 6 days

No. of days in the month August = 31 days

No. of days from 1st September to 25th September = 25 days

Now we have to add all the days means we get the answer

Total days = 6 + 31 + 25 = 62 days.