Find the total cost of digging a well of depth 25m, after every meter
of digging, when it costs Rs.150 for the first meter and rises by Rs.50
for each subsequent meter
Answers
Answered by
1
Explanation:
here , use the property , sum of n terms of an A.P.
so,
S25 = 25/2 {150 + (25-1)50}
= 16875
therefore , the total cost of digging the well = Rs.16875