Math, asked by wahuwaningi, 5 hours ago

Five men can finish work in 20 days. How long will four men take?​

Answers

Answered by pravinpatilpp404
0

Step-by-step explanation:

inverse proportion

(5*20)=(4*x)

5*20/4=x

25

so four men woul take 25 days to complete it