Five workers take 12 days to weed a
field. How many days would 6 workers
take ? How many would 15 take ?
Answers
Answered by
1
Step-by-step explanation:
10 days and 4 days are the answer for above question
Attachments:
Answered by
29
Let us suppose 6 workers will take x days to weed a field.
As the number of workers increases, the number of days decreases.
So, the number of workers and number of days are in inverse proportion.
=> 5 × 12 = 6 × x
=> x = 60/6
=> x = 10
Let us suppose 15 workers will take y days to weed a field.
therefore, 5 × 12 = 15 × y
=> y = 60/5
=> y = 4 days
Hence, 6 workers will take 10 days, while 15 workers will take 4 days to weed a field.