Five workers take 12 days to weed a field.How many days would 15 take ?​

Answers

Answered by shachimishra88
0

Answer- 4

step by step-if 5 workers take 12 days

then , 1 worker will take = 5×12=60days

so ,6 workers will take =60÷6=10

and that of 15 workers will take = 60÷15 = 4

Answered by aftabahemad
0

As per the data given in the question,

We have to determine that in how many days does the 15 workers complete the same work which is completed by 5 workers in 12 days.

As we know that,

The total work is = Workers\:\times Number\:of\:days

So, total unit of work will be =(5\times 12) = 60\:units

As the same 60 units of work is needed to be completed by 15 men.

So, for finding the number of day required we will divide the total work by number of workers.

So, total number of day taken will be =\frac{60}{15} = 4\:days

Hence, 15 workers complete the same work in 4 days which is completed by 5 workers in 12 days.