five workers take 12 days to weed a field. how many days would 6 workers take?​

Answers

Answered by jammubassboosters
1

Answer:

beta if we decide 5÷12 it will make 2.5 ans so the correct answer is tuesday

Answered by raptorstrike6
2

Answer:

10 days

Step-by-step explanation:

amount of weeds=5×12=60

take x as days taken by 6 workers to weed the field

so 6x=60

x=60/6

x=10

so 6 workers would take 10 days to weed the field