Five workers take 12 days to weed a field. How many days would 6 workers take? How many would 15 take?
Answers
Answered by
18
5 workers can finish the work of field in 12 days
then 1 worker will complete the work
in = 5 × 12 = 60 days
6 workers will complete the work
in = 60 ÷ 6 = 10 days
15 workers will complete the work
in = 60 ÷ 15 = 4 days
Answer:
________
6 workers would take 10days and 15 workers would take 4 days .
then 1 worker will complete the work
in = 5 × 12 = 60 days
6 workers will complete the work
in = 60 ÷ 6 = 10 days
15 workers will complete the work
in = 60 ÷ 15 = 4 days
Answer:
________
6 workers would take 10days and 15 workers would take 4 days .
Answered by
1
Let us suppose 6 workers will take x days to weed a field.
As the number of workers increases, the number of days decreases.
So, the number of workers and number of days are in inverse proportion.
=> 5 × 12 = 6 × x
=> x = 60/6
=> x = 10
Let us suppose 15 workers will take y days to weed a field.
therefore, 5 × 12 = 15 × y
=> y = 60/5
=> y = 4 days
Hence, 6 workers will take 10 days, while 15 workers will take 4 days to weed a field.