five workers takes 6 days to complete work how much days 3 worker will take
Answers
Answered by
4
Step-by-step explanation:
No. of days taken by 5 workers to complete the work = 6 days
No. of days taken by 1 worker to complete the work= 6 multiplied by 5 = 30days
No. of days taken by 3 workers tp complete the work = 30/3 = 10 days
Similar questions
Physics,
5 months ago
History,
5 months ago
Social Sciences,
5 months ago
Math,
10 months ago
Math,
1 year ago