Five workers to take 12 days
to weed
field. How many days
would 6 works take ?
Answers
Answered by
11
Answer:
10days
Step-by-step explanation:
5 workers=12 days
1 worker=12×5=60days
6 workers=60/6=10days
Answered by
0
Answer:
10 days
Step-by-step explanation:
5workers weed the field in = 12 days
1 worker weed the field in = (12×5) days
6workers weed the field in =60/6
=10 days