Following was determined for an activity
Optimistic Time = 4 days Pessimistic Time =
12 days Most likely time = 5 days What will
be the variance for activity?
O 1.33
O 1.768
O 1.15
O 1.13
Answers
Answered by
1
Given:
Optimistic Time = 4 days
Pessimistic Time = 12 days
Most likely time = 5 days
To find:
What will be the variance for activity?
O 1.33
O 1.768
O 1.15
O 1.13
Solution:
There are three types of Estimations.
1) Optimistic Estimate:
- This is the shortest duration of time in which an activity/project can be done. It is denoted by ''To''.
2) Pessimistic Estimate:
- This is the longest duration of time in which an activity/project can be done. It is denoted by ''Tp''.
3) Most Likely Estimate:
- This is the estimation of the general time in which the activity/project can take place. Here, the chance of finishing an activity/project is highest. It is denoted by ''Tm''.
Formula to find the variance of an activity:
''Tp'' is Pessimistic time and ''To'' is Optimistic time.
Tp is given as 12 days
To is given as 4 days.
Hence, among the given options the required answer is 1.768
Answered by
0
Answer:
Explanation:5. If 4u + 3 = 6 + 2u, then u = _________.
Similar questions