For a 14-person team, how does the actual weekly labour cost compare to the targeted labour cost?
– Regular Rate $15.00/hr
– Overtime Rate $22.50/hr
– Targeted Labour Cost $12,000/wk
– Labour Hours Needed 800/wk
– Any hour worked over 40 hrs/wk must be paid overtime rate
Answers
Answered by
5
Answer:
d) any hour worked over 40 hrs/ wk must be paid overtime rate
Answered by
0
Answer:
240 hours
Step-by-step explanation:
Concept
- Target costing is a system under which a company plans in advance for the price points, product costs, and margins that it wants to achieve for a new product.
Given
Regular Rate $15.00/hr
Overtime Rate $22.50/hr
Targeted Labour Cost $12,000/wk
Labour Hours Needed 800/wk
Solution
Overtime means each employee can work beyond the input of 40 hrs. Per week.
Labor requirement = 800 hrs.
14 men labor capacity = 14× 40 = 560 hrs.
So overtime hours required = 800-560=240 hrs