For asfalting of a road 10 workers require 4 days. So to complete the same work how many days will be required for 8 workers?
Answers
Answered by
1
Answer:
4 hours x 12 days=48 total hours worked
48 hours x 10 men=480 man/hours
1 man/480 total hours=1/480th of the work done per man per hour
8 x 6 x 1/480=1/10 work done per day
1 work / 1/10 work done per day=10 days necessary to finish the work.
Answered by
1
Answer:
For asfalting of a road 10 workers require 4 days. So to complete the same work how many days will be required for 8 workers?
Explanation: