For constructing one well 5 labour requires 12 days , then how many labour will be required to complete the same in 4 days ?

Answers

Answered by VivianHew
1

Answer:

15

Step-by-step explanation:

12/4=3

5x3=15

cuz it takes more people to take less time.

Answered by nimisha125
0

15 labour.

5×12=x×4

5×12/4=x

therefore, x=15