for doing some work, ganesh takes 10 days more than that of gajanan. if they work together, the work gets completed in 12 days. howd many days will it take if ganesh works alone?
Answers
Answered by
5
Answer:
Together they complete the work in 12 days.Number of days can't be a negative number so the value of x is 20. Thus, Gajanan takes 20days. Ganesh takes 10 days more than Gajanani.e 30 days