For production of 1600 units, actual labour cost
is Rs 96030 and 19800 labour hours are actually
worked, then the actual labour rate is___
per hour
a.Rs 60.02
b.Rs 4.85
c.Rs 12.34
d.Rs 8.45
Answers
Answered by
0
Answer:
option C is correct
Explanation:
plz mark me brilliant answer and like me