For production of 1600 units, actual labour cost
is Rs 96030 and 19800 labour hours are actually
worked, then the actual labour rate is________?
per hour
a.Rs 60.02
b.Rs 4.85
c.Rs 12.34
d.Rs 8.45
Answers
Answered by
1
Answer:
Answe is(c)
Explanation:
actual labour hours/production units
=19800/1600
=12.375 i.e., 12.34