Math, asked by pankajpatil1976, 1 year ago

For tree plantation 30 workers dig 20 pits in 40 days. If 40 workers have to dig 30 pits, how many days will be require?

Answers

Answered by 12382
1
60 days will be required

Vishwal: Will you explain it
Answered by Ezekiel9
4
20 days would be required.

Vishwal: Pls explain