From the following detail ,find out the machine hour rate. standing charges per hour Rs.2.50,Depreciation of machine per hour Rs.5,Repair charges 50% of depreciation, the machine consumes 10 units of electric power per hour @40 paise per unit
a)17
b)14
c)16
d)16
Answers
Answered by
0
Answer:
increase points
Explanation:
Answered by
0
Rs 14 is Machine Hour Rate
Explanation:
standing charges per hour = Rs 2.5
Depreciation of machine per hour = Rs 5
Repair charges 50% of depreciation, = (50/100)5 = Rs 2.5
Electricity consumption Charges = 10 * (40/100) = Rs 4
Machine Hour Rate = 2.5 + 5 + 2.5 + 4 = 14 Rs