Math, asked by abul27nandhini03, 23 days ago

From the following information, calculate the

value of work-in-progress

Rs.

Total cost of contract to date 3,83,000

Cost of contract not yet to certified 23,000

Value of work certified 4,20,000

Cash received to date 3,78,000​

Answers

Answered by stsujon81
0

Step-by-step explanation:

Total cost of contract to date 3,83,000