Accountancy, asked by raihan1999, 8 months ago

From the following particulars calculate
1)Labour cost variance and
Labour Rate vairance.
Standard hours- 120 houn
Standard Rate - Rs. 40 per hour
Actual Hours- 160 hours
Actual Rate-Rs. 50 per hour​

Answers

Answered by shruti6687
2

Answer:

Standard Rate per hour = Rs. 50. Actual Production = 2,000 units. Actual Hours = 35,000 hours. Actual rate per hour = Rs. 40.