From the given information, calculate prime cost- Raw material consumed:
Rs.4,10,000/- Direct wages: Rs.70,000/- Direct expenses: Rs.40,0001- Factory
overhead: Rs. 50,000/-
O Rs.1,10,000
O Rs.5,20,000
O Rs.5,70,000
O Rs.1,60,000
Answers
Answered by
9
Answer:
prime cost = 410000+70000+40000+50000=570000
Answered by
1
Prime cost will be ₹520000.
Explanation:
Given: Raw material consumed:Rs.4,10,000/-
Direct wages: Rs.70,000/-
Direct expenses: Rs.40,000/-
Factory overhead: Rs. 50,000/-
Asked: Prime cost
Formula: Prime cost = All direct cost
Solution:
- Prime cost is the cumulation of all the direct cost associated with the product, it does not includes fixed cost.
- Prime cost = Direct material + direct wages + direct expenses.
- Prime cost = 410000+70000+40000 = ₹520000
- Thus, the prime cost will be ₹520000.