Geeat can do a piece of work in 6 days and Meeta can do the same work in 12 days. How many days will they to do it together?​

Answers

Answered by kperiyasamy624
1

Answer:

hi..

Step-by-step explanation:

A → 6 days

B → 12 days

LCM =12 units which is the total work

A 1 day work = 2 units.

B 1 day work =1 unit

A+B 1 day work =3 units

Together they can complete the work in 12/3= 4 days